Ellesborough Road Closure UPDATE
05/03/2023
Good afternoon,
I would just like to update you on the works on Ellesborough Road.
The trail hole activity reached a point this afternoon where we have been able to complete the first phase of the works and reopen the road for the weekend. The works have not been completed entirely and we need to excavate further trail holes next week on the western end of the temporary diversion close to where the old road and the new road will knit together and where Bacombe Lane will connect.
I appreciate these works are very inconvenient but hopefully this should more comfortable movement over the weekend. The road will close again on Monday morning at around 8am and remain closed until 12th March.
Kind regards
Jon Deas
Engagement Manager
Eiffage Kier Ferrovial BAM JV | HS2 Team | 5th Floor, Exchange House, 450 Midsummer Blvd, Milton Keynes, MK9 2EA